Temporary shoring has to do more than carry load. It must fit the building, the available equipment, and the work sequence.
At a university library, crews needed to create elevator and mechanical shaft openings through an existing concrete pan-deck floor. The floor had to remain supported during demolition and new concrete beam work, while the shoring fit around existing framing and left room for crews to work below.
SD&C was initially brought in to help with the demolition shoring. As planning moved forward, the concrete contractor also needed shoring to install the new concrete beams. SD&C already had an established working relationship with that contractor, and the project included an additional shoring phase for the concrete work. As time was of the essence, it made sense for SD&C to stay involved across both phases and coordinate the floor support as one staged effort.
Steel beams bearing on scaffold towers to support the remaining deck.
The Situation
The floor framing plans identified two types of openings on 4 different levels:
Elevator shaft opening, requiring demolition of existing concrete joists.
Mechanical shaft openings, also requiring demolition of existing concrete joists.
The planned work included one Elevator Shaft opening and two Mechanical shaft openings at each floor. Shoring was planned in two-floor stages. After the new concrete beams were installed and cured, the team could move the equipment to the remaining floors.
Designing for Changing Conditions
The shoring design considered two construction conditions at each opening:
Existing-joist demolition: the area being demolished, the tributary floor area remaining and temporarily supported, and construction live load.
New-beam placement: the weight of the proposed beam, the tributary floor area remaining and temporarily supported, and construction live load.
The calculated dead load was 100 psf. A 50 psf construction live load brought the total design floor load to 150 psf. The analysis also included the dead load of the proposed concrete beams at the openings.
The planned load path used 3/4-inch plywood, SPF No. 1 2×6 framing members, 7.5-inch Aluma stringer beams, W10×19 steel headers, WACO Hi-Load shoring frames, and 2×8 mudsills. The supporting floor below is part of that load path too: reactions continue through the mudsills and into the structure beneath the shoring.
How the Load Gets Down
Steel headers and stringer beams collect loads from the supported floor and transfer them to the shoring frames. The frame legs bear on 2×8 mudsills, which distribute the reactions to the supporting floor system below.
The full load path—from the supported floor to the structure beneath the shoring—must be checked.